This page provides you with the real and most updated / latest Certification Question with Correct Answers for the Quality Management with SAP ERP 6.0 EHP5 (C_TPLM40_65). We at ERPKITE providing these questions for free to all the SAP certification candidate to showcase the quality of the question prepared by our SAP subject experts.

 

We have developed an advanced methodology to prepare for the SAP QM (C_TPLM40_65) exam to make it easy for anyone to pass the SAP C_TPLM40_65 certification and be certified on the Quality Management with SAP ERP 6.0 EHP5. The methodology is practice to learn, as the memory principle and many deep research suggest, the practice could lead to a very long-lasting memory.

 

Highly Recommended Practice test: SAP QM PRACTICE TEST
Complete Syllabus: SAP C_TPLM40_65 Syllabus

 

SAP QM (C_TPLM40_65) Free Sample Questions

QUESTIONS:

01. You want to record defects in inspection lot processing. In the Implementation Guide (IMG), which elements can you combine in a defect report type?
Please choose the correct answer.

a) Confirmation Profile, Catalog Profile, Notification Type
b) Confirmation Profile, Defect Class, Origin of the Catalog Profile
c) Confirmation Profile, Catalog Profile, Defect Type, Work Center
d) Confirmation Profile, Catalog Profile, Origin of the Catalog Profile

 

02. When you activate QM in the material master in Procurement, to which organizational level does the function apply?
Please choose the correct answer.

a) Controlling area
b) Client
c) Plant
d) Company code

 

03. During quality inspection archiving, in which sequence must the system process the data?
Please choose the correct answer.

a) Single Results, Characteristics and Operations, Samples, Inspection Lots
b) Inspection Lots, Characteristics and Operations, Samples, Single Results
c) Samples, Single Results, Characteristics and Operations, Inspection Lots
d) Single Results, Samples, Characteristics and Operations, Inspection Lots

 

04. What is the maximum number of function modules you can assign to a single follow-up action for the usage decision in the Implementation Guide (IMG)?
Please choose the correct answer.

a) One
b) Zero
c) Ninety-nine
d) Unlimited

 

05. What do you set up when implementing a DP scenario?
Please choose the correct answer.

a) Cost center
b) Control key
c) General ledger
d) Hourly wages

 

06. You want to collect costs for repair work. What must you define in the work center?
Please choose the correct answer.

a) Activity types
b) Formulas
c) Set-up time
d) Cost center

 

07. What Quality Management master data does an inspection with defect recording require?
Please choose the correct answer.

a) Task list
b) Catalogs
c) Inspection methods
d) Master inspection characteristics

 

08. On which structure level can you control Sales and Distribution processes within QM for material and customer data?
Please choose the correct answer.

a) Company code
b) Sales organization
c) Distribution channel
d) Customer sales area

 

09. Which type of task list defines process steps independently of the inspection lot?
Please choose the correct answer.

a) Routing
b) Inspection plan
c) Reference object set
d) Master recipe

 

10. When you create a task list for an inspection lot, which objects are available for inspection?
There are 2 correct answers to this question.

a) Equipment
b) Batch
c) Handling unit
d) Material

 

11. Planned orders are scheduled in SNP with just one PDS for a product. How is the duration and end date of the order derived, if you plan in weekly buckets?
There are 3 correct answers to this question.

a) Results Recording
b) Control Charts

c) Usage Decision
d) Results History
e) Defect Recording

 

12. During an audit you document a finding. In the audit structure, what can link an audit and a quality notification?
Please choose the correct answer.

a) Corrective/preventive action
b) Audit question
c) Business partner
d) Attached document

 

13. Your customer requires the receipt of incoming certificates. Where do you allocate the certificate type when you activate Quality Management (QM) in Procurement?
Please choose the correct answer.

a) In the vendor master record
b) In the Q-info record
c) In the inspection plan
d) In the material master

 

14. Which of the following charts take into account only internal process parameters and not external tolerance specifications?
Please choose the correct answer.

a) Shewhart Chart
b) Planning Control Chart
c) Acceptance Chart
d) Western Electric Chart

 

15. To which notification structure elements or objects can you assign catalog types?
There are 3 correct answers to this question.

a) Action
b) Documents
c) Partner
d) Task
e) Header

 

16. Which of the following controls a sample-managed process?
Please choose the correct answer.

a) Sample determination
b) Sample procedure
c) Sample plan
d) Sample draw

 

17. Which objects can you add as elements to the action box of a notification type in the implementation guide (IMG)?
There are 2 correct answers to this question.

a) Activities
b) Follow up actions
c) Documents
d) Tasks

 

18. Which dynamic modification levels exist in the inspection plan?
There are 3 correct answers to this question.

a) Dynamic modification at character level
b) Dynamic modification at operation level
c) Dynamic modification at material level
d) Dynamic modification at inspection type level
e) Dynamic modification at lot level

 

19. After you have approved all physical sample documents for a stability study, how do you close the corresponding inspection lots?
Please choose the correct answer.

a) Remove the samples from storage.
b) Archive physical sample documents.
c) Change the test scheduling.
d) Make a usage decision.

 

20. When you perform calibration inspections, which objects do you combine with maintenance items in a maintenance plan?
Please choose the correct answer.

a) Scheduling parameters and maintenance task lists
b) Scheduling parameters and maintenance orders
c) Scheduling parameters and inspection lots
d) Inspection characteristics and inspection plans

 