Highly Recommended Practice test: | SAP SD PRACTICE TEST |
Complete Syllabus: | SAP C_TSCM62_67 Syllabus |
SAP SD (C_TSCM62_67) Free Sample Questions
QUESTIONS:
01. How can you limit the number of master data objects to be created when the manufacturing process is the same for many different products?
Please choose the correct answer.
a) By creating routings with alternative sequences
b) By assigning the same production version to different materials
c) By assigning different materials to the same routing
d) By creating routings with parallel sequences
02. Which elements are included in the structure of the batch where-used list?
There are 3 correct answers to this question.
a) Purchase orders
b) Planned orders
c) Transfers from batch to batch
d) Stock transfers
e) Collective orders
03. You want to procure your material components based on a forecast for the finished material derived from historical sales. When customers order, you produce the finished product and reserve it for that particular order.
Which is the appropriate planning strategy to use?
Please choose the correct answer.
a) Production by lot size (30)
b) Planning without final assembly (50)
c) Planning with final assembly (40)
d) Make-to-order production (20)
04. In which ways can you implement confirmations for production orders?
There are 2 correct answers to this question.
a) Through a SAP Manufacturing Intelligence and Integration (SAP MII) server
b) Through the Advanced Planning and Optimization (APO) component
c) Through the SAP Integrated Business Planning (SAP IBP) cloud solution
d) Through automatic process messages using SAP NetWeaver Process Integration (PI)
05. Which of the following are prerequisites for running MRP in a plant?
There are 3 correct answers to this question.
a) Assign a valid planning strategy
b) Set up the planning file
c) Activate requirements planning
d) Configure MRP groups
e) Maintain plant parameters
06. Which of the following options can you use for automatic line loading of planned orders on available production lines?
There are 3 correct answers to this question.
a) Planning table
b) Quota arrangement
c) Sequencing
d) Selection method
e) PP/DS heuristics
07. Which object in customizing controls the determination of planned total overhead process costs for production orders?
Please choose the correct answer.
a) Cost log
b) Accounting type
c) Costing variant
d) Settlement profile
08. For which planning strategy does the reduction of planned independent requirements always occur with the goods receipt?
Please choose the correct answer.
a) Planning with final assembly (40)
b) Gross requirements planning (11)
c) Planning without final assembly (50)
d) Net requirements planning (10)
09. What happens when a repetitive manufacturing planned order is assigned to a production line in the planning table?
There are 2 correct answers to this question.
a) The planned order generates capacity requirements.
b) The planned order is converted to a production order.
c) The system status of the planned order changes.
d) The planned order type changes.
10. The settings for MRP can be maintained at different levels. If settings have been maintained in different places, in which sequence does the system search for the MRP settings?
Please choose the correct answer.
a) Plant Settings → MRP Group → Material Master
b) Material Master → Plant Settings → MRP Group
c) Material Master → MRP Group → Plant Settings
d) MRP Group → Material Master → Plant Settings
11. What sequence do you follow in master data maintenance to define the production of a material?
Please choose the correct answer.
a) Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing
b) Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
c) Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing
d) Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
12. Which BOM selection possibilities are available for opening a production order?
There are 2 correct answers to this question.
a) Selection by BOM number in the material master of the material to be produced
b) Selection using a production version
c) Manual selection
d) Automatic selection controlled by Customizing settings
e) Selection using the production scheduling profile
13. Which of the following functions does SAP Supply Chain Management (SCM) offer?
Please choose the correct answer.
a) Planning and optimization of supply chains across company boundaries.
b) Optimization of the procurement strategy with the supplier pool.
c) Product development, safety, quality, and maintenance.
d) Communication to customers through different interaction channels.
14. Which of the following organizational units can be used for planning and manufacturing in an SAP ECC system?
There are 3 correct answers to this question.
a) Distribution channel
b) MRP area
c) Sales Location
d) Sales area
e) Storage location
15. When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
Please choose the correct answer.
a) Interactive single-item planning for the delayed assembly
b) Multi-level single-item planning with the “simulation mode” option
c) Total planning online
d) Multi-level single-item planning with the “display material list” option
16. Which statements about the reorganization of planned independent requirements in SAP ECC are true?
There are 2 correct answers to this question.
a) The reorganization only affects planned independent requirements that lie on a time axis to the past from a specified key date.
b) The reorganization can be parameterized using a plant-specific reorganization interval.
c) The reorganization only deletes planned independent requirements that have no fixed planned orders to them
d) The reorganization is a form of demand adjustment in which non-settled planned independent requirements for the planning are set to inactive but are not deleted.
17. What is a feature of the simulation mode for material requirements planning in SAP ECC?
Please choose the correct answer.
a) It posts planning results to the database automatically.
b) It propagates exception messages from a component to the finished product.
c) It calculates the delay time which may occur in planning.
d) It triggers multilevel bottom-up scheduling.
18. Where can you maintain available capacities in an SAP ECC system?
There are 2 correct answers to this question.
a) Routing
b) Production supply area
c) Pooled capacity
d) Work center
19. You set a rolling planning time fence (firming type = 1) for a material in an SAP ECC system. When an unforeseen production failure occurs, firmed planned orders might fall into the past.
How can these firmed planned orders be deleted automatically?
Please choose the correct answer.
a) Activate demand adjustment in Customizing.
b) Use an MRP type in which the roll-forward.
c) Use reorganization.
d) Use an MRP type in which the roll-backwards mechanism is activated.
20. Which of the following statements about consumption are correct?
There are 2 correct answers to this question.
a) Consumption takes place on the material level between the planned independent requirements and the planned orders.
b) Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
c) Consumption is restructured with the planning run.
d) Consumption can take place between order reservations and planned independent requirements, depending on the strategy.
21.Which activity can trigger an automatic availability check for the components of a production order?
Please choose the correct answer.
a) Material staging
b) Order rescheduling
c) Order release
d) Goods receipt for a missing part
22. During the implementation of SAP ECC material requirements planning, the project team defines MRP controller numbers in Customizing under the entry “Define MRP Controller” that can be assigned to the planners responsible for the material.
Which of the following statements are correct concerning these MRP controllers?
There are 2 correct answers to this question.
a) The MRP controller number is a central selection
b) A planner responsible for a material can have multiple MRP controller numbers.
c) In multilevel single-item planning, materials are selected using the MRP controller number.
d) The MRP controller number is assigned using the production version.
23. Which of the following scheduling types can only be used in capacity planning?
Please choose the correct answer.
a) Midpoint
b) Forward
c) Only capacity requirements
d) Backward
24. The company you are advising uses a plant data collection system from company XYZ and would like to distribute production orders to the terminals on this system and enter feedback using these terminals.
Which integration possibilities would you recommend so that as little work as possible is required for the customer to implement this?
Please choose the correct answer.
a) SAP Manufacturing Integration and Intelligence (SAP MII)
b) The plant data collection interface (PP-PDC)
c) Execution Steps (XSteps)
d) The process control system interface PI-PCS
25. The final assembly of a finished product should only be triggered when a customer order arrives. Which planning strategy for the finished product do you use?
Please choose the correct answer.
a) Planning with make-to-stock (strategy 10)
b) Planning at the assembly level (strategy 70)
c) Planning without final assembly (strategy 50)
d) Planning with final assembly (strategy 40)
26. Which options can you use to convert planned orders into production orders in the SAP ECC system?
There are 3 correct answers to this question.
a) Mass processing
b) Automatically in the planning run (MRP)
c) Background processing in a program
d) Customizing for the planned order
e) Order progress report
27. You want to use the function “Read PP master data” in the production order. However, while calling the function you receive an error message. What could be the reason?
Please choose the correct answer.
a) The material availability check has been performed.
b) Goods movements have been posted.
c) The production order has been released.
d) Order papers have been printed.
28. Which statements about the reorganization of planned independent requirements in SAP ECC are true?
There are 2 correct answers to this question.
a) The reorganization only affects planned independent requirements that lie on a time axis to the past from a specified key date.
b) The reorganization can be parameterized using a plant-specific reorganization interval.
c) The reorganization only deletes planned independent requirements that have no fixed planned orders to them.
d) The reorganization is a form of demand adjustment in which non-settled planned independent requirements for the planning are set to inactive but are not deleted.
29. Which types of objects can be changed with Engineering Change Management (ECM)?
There are 3 correct answers to this question.
a) Task list
b) Work center
c) Production version
d) Bill of material
e) Material master
30. Which BOM selection possibilities are available for opening a production order?
There are 2 correct answers to this question.
a) Manual selection
b) Automatic selection controlled with Customizing settings
c) Selection by BOM number in the material master of the material to be produced
d) Selection using the production scheduling profile
e) Selection using a production version
31.You want to use production/resource tools in your manufacturing process. Which production type do you use?
Please choose the correct answer.
a) Repetitive manufacturing
b) Production order
c) Process order
d) KANBAN
32. What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements?
There are 3 correct answers to this question.
a) Availability check
b) Digital signature
c) Resource selection
d) Electronic batch record
e) Approved master recipes
33. When scheduling a routing in the SAP ECC system, which of the following time elements is a interoperation time?
Please choose the correct answer.
a) Safety time
b) Float before production
c) Processing time
d) Setup time
34. Which functions can be triggered before releasing a production order?
There are 3 correct answers to this question.
a) Confirmation
b) Selection of a routing
c) Scheduling
d) Stock determination
e) Selection of a BOM
35. What does SAP ERP mean?
Please choose the correct answer.
a) SAP ERP is a planning system in which extended planning processes can be mapped.
b) SAP ERP is a system hardware that includes modules for purchasing, sales and distribution, materials management, production and so on.
c) SAP ERP is a technological platform, on the basis of which customer-specific extensions can be imported.
d) SAP ERP is an application that an enterprise can use to manage its business processes efficiently.
36. How can you convert planned orders into production orders in an SAP ECC system?
There are 3 correct answers to this question.
a) Automatically, in the planning run (MRP)
b) Set the conversion indicator in Customizing for the planned order.
c) Use mass processing.
d) Use the order progress report.
e) Use background processing.
37. Which SAP NetWeaver component realizes cross-system application processes?
Please choose the correct answer.
a) SAP Business Warehouse (SAP BW)
b) SAP Enterprise Portal (SAP EP)
c) SAP Master Data Management (SAP MDM)
d) SAP Exchange Infrastructure (SAP XI) / SAP Process Integration (SAP PI)
38. You are using MRP controllers in an SAP ECC system. Which of the following statements concerning MRP controllers are correct?
There are 2 correct answers to this question.
a) The MRP controller is maintained in production versions.
b) In multilevel single-item planning, materials are selected using the MRP controller.
c) An employee responsible for the planning of materials can be assigned to multiple MRP controllers.
d) The MRP controller is a central selection criterion for evaluating material requirements planning.
39. Where can you define the valid receivers for production order costs?
Please choose the correct answer.
a) In the valuation variant
b) In the production scheduling profile
c) In the settlement profile
d) In the costing variant
40. For which of the following objects can you enter a confirmation?
There are 2 correct answers to this question.
a) Production order
b) Production order operation
c) Trigger Point
d) Work Center
If you have any feedback, pl send us on hello@erpkite.com